The latest CERT construction and property management update is here. Explore our recent progress across our developments and find out our highlights so far this year. 

CERT News

Meadow Mill

Meadow Mill, a 151,000 sqft development located in Stockport comprised of 213 apartments plus commercial units at ground level, is the latest addition to CERT’s estate management portfolio. In a unique position to offer both estate management and individual property management, investor landlords will be able to benefit from having a single company manage the letting of their apartments as well as the overall building management, creating a seamless service and removing the headache of liaising between different entities. With 30% of the building now complete, the remaining apartments will reach practical completion throughout the remaining duration of the year.

Meadow Mill is available to invest in now and – completing over the coming months – will be income generating this year. Want to learn more about Meadow Mill, and how to invest in the project?

Contact: jameslogan@certproperty.co.uk / +44 161 2411008

CERT Construction

Osborne Yard

Osborne Yard saw piling complete in Q1, totaling 281 piles each down to a depth of 18 meters. Pile caps are now being created and sub-ground level drainage being installed. The steel frame is in the final stages of design and will be in production in early Q2, ready to start arriving on site a month later and be erected – a process that will take up to 14 weeks. The project will consist of 83 apartments and 7 townhouses.

SONA

SONA is unveiled further as the scaffolding continues to come down, showcasing the completed external elevations. As the scaffolding is removed from the internal atrium, works have commence on the ground floor areas previously inaccessible. Drainage is now able to be completed and the concrete pour is underway on the ground floor. With all but 4 apartments now complete, the project is on track for completion in Q3.

SONA - CERT Property Investment, Development & Management

Peelers Yard

Full construction works commenced at Peeler’s Yard in January, our latest BTR scheme located in New Cross, Manchester. Two months in and all 218 piles were completed, with the basement level now being dug out and sub-floor utilities being installed. The light-weight metal frame will soon be arriving on site, to be erected in Q2. The project will see 82 x 1 and 2 bed apartments delivered, designed with open plan living spaces incorporating high specification contemporary kitchens and bathrooms. The building has been designed to combine new-build elements within the retained historic structures of the site, which includes the landmark chimney from the 1800’s police station.

 

Want to keep updated with our construction updates? Stay connected with us on our social media.